Follow the 3-stage process to generate Internationally Transferrable Mitigation Outcomes (ITMOs) under the Singapore-Rwanda Implementation Agreement.
There are 3 stages to generate Internationally Transferrable Mitigation Outcomes (ITMOs) under the Singapore-Rwanda Implementation Agreement (IA).

Stage A – Submission of Proposed Mitigation Activity
The project applicant submits the completed Singapore-Rwanda Mitigation Activity Note of Intent (in English) to the Joint Committee.
If the Mitigation Activity Note of Intent is accepted by both countries, the Joint Committee will forward to the project applicant the Letter of Support and Letter of Intent from Singapore and Rwanda respectively. These letters may specify the conditions that the project applicant should meet in designing the proposed mitigation activity.
If the Mitigation Activity Note of Intent is not accepted, the project applicant will be informed, along with any reasons for the non-acceptance (if relevant).
Documents to be submitted
Singapore-Rwanda Mitigation Activity Note of Intent
Company Registration Certificate (if applicable, for companies)
Legal Personality Certificate (if applicable, for Non-Governmental Organisations (NGOs))
Singapore and Rwanda may request for the submission of other relevant documents not listed above.
Stage B – Authorisation of Proposed Mitigation Activity
The project applicant submits the completed Singapore-Rwanda Authorisation Application Form (in English) to the Joint Committee.
If the Request for Authorisation is accepted by both countries, the Joint Committee will:
Forward to the project applicant the Letters of Authorisation issued by Singapore and Rwanda respectively
Enter the mitigation activity into the Project Register; and
Issue a Joint Statement of Authorisation to the project applicant, and publish it online.
The project applicant may then proceed with the registration of the mitigation activity with the carbon crediting programme specified in the Letters of Authorisation and inform the Joint Committee of the successful registration. The project applicant may then proceed with the implementation of the project.
If the proposed mitigation activity is not authorised, the project applicant will be informed, along with any reasons for the non-acceptance (if relevant).
Documents to be submitted
Singapore-Rwanda Authorisation Application Form
Validated Project Design Document
Validation Report in accordance with the requirements of the carbon crediting programme
[Where relevant] Supporting documents for land-based and technology-related projects (e.g. laboratory testing certificate for clean cookstove projects)
Proof of ownership of, or control over, project assets (e.g. land titles, notarised leases, Memorandums of Understandings (MoUs) etc.)
Partnerships or collaboration agreement in the case of multi-party projects, showcasing clear emissions reductions claim rights
Evidence of consent from relevant ministries or local authorities i.e. a recommendation letter
Letter of Intent issued by the Rwanda Government
[If relevant] Offer to the Singapore Government for purchase of ITMOs arising from this mitigation activity that are authorised under this IA
Singapore and Rwanda may request for the submission of other relevant documents not listed above.
Stage C – ITMOs Issuance Authorisation
The Project Participant submits the completed Singapore-Rwanda ITMO Issuance Application Form (in English) to the Joint Committee.
If the ITMO Issuance Application Form is accepted by both countries, the Joint Committee will forward to the project applicant the Letter of Positive Examination issued by Rwanda.
If the proposed ITMO issuance is not authorised, the project applicant will be informed, along with any reasons for the non-acceptance (if relevant).
Documents to be submitted
Singapore-Rwanda ITMO Issuance Application Form
Proof of Issuance from Carbon Crediting Programme with Accompanying Verification Report
Evidence of settlement of the Corresponding Adjustment Fee (CAF) for past ITMOs authorised for this mitigation activity under this IA from the project to Rwanda’s Fund
Documentary evidence that clearly shows compliance with the transfer of 1% of the past ITMOs authorised for this mitigation activity under this IA from the project to the National Buffer Account of Rwanda
Other supporting documents as required in the form
Singapore and Rwanda may request for the submission of other relevant documents not listed above.